We’re back in Salinas, CA!

April 19, 2018

On Thursday, April 12th, the team disassembled equipment from the Yuma plant and moved 600 miles away to Salinas, CA.  On Friday, most everything was installed and Saturday we tested to make sure the belts moving in the right direction, pumps are working and product is flowing.  We then turned the plant over to our sanitation team for 12 hours to clean from top to bottom before starting production back up on Sunday morning, 4/15/18.  Thank you to all of our transportation partners, contractors and move crew for another successful transition!